Transfer area at Carl Jacobsens Vej
At the transfer area, work continues on new lifts for track 2 of the Køge Bugt railway - we expect to complete this in late spring. In addition, we are carrying out a number of minor granite works on the stairs and other minor works on stairs, lifts and escalators.
Øresund platforms and the pedestrian tunnel under the Øresund tracks
At the Øresund tracks and the pedestrian tunnel under the tracks to the Følager area, we continue with the final concrete works. At the same time, we're setting up granite and installing stairs, as well as furnishing the technical rooms.
New stairs and lift for Køge Bugt track 1
During April, work will begin on establishing a new staircase and lift just south of the Køge Bugt line between the Øresund tracks and the Copenhagen-Ringsted line. The work will take place in a small area in extension of the former construction site at Strømmen. Initially, we will establish the workplace and prepare for further work. The work will take place during daylight hours unless we notify otherwise via SMS.
More information
We apologise for any inconvenience this work may cause. If you have any questions about the work, please contact us at nabo@m.dk or +45 72 30 20 20.